| Campus Project
List ( 110
Projects ) |
||
As of Wednesday, May 16, 2012 |
Current
University Of Maryland Design and Construction Campus Projects |
Facilities Management |
|---|
| STATUS | CAMPUS | TOTAL BUDGET |
DESIGN START |
CONST START |
CONST COMP |
|
Construction - Active |
UMCP | ART/SOC DESIGN AND INSTALL GUARDRAILS | $33,000 |
NA |
May 2012 |
May 2012 |
Construction - Active |
UMCP | AVRUM GUDELSKY VET SCI. - SUITE 1143 HVAC RENOVATION | $138,000 |
Sep 2011 |
Feb 2012 |
May 2012 |
Construction - Active |
UMCP | AVW HOT WATER HEATING LINE FLOOD ON 3/10/2012 | $40,000 |
NA |
Apr 2012 |
May 2012 |
Construction - Active |
UMCP | BIO-PSYCH BLDG. - TESTING CTR STE 0146/0150 FOR DR. J. BEIER | $128,000 |
May 2011 |
Jan 2011 |
May 2012 |
Construction - Active |
UMCP | BIO-PSYCH. BLDG. RM. 4150/4150A RENOV. FOR DR. MOSS | $102,000 |
Sep 2011 |
May 2012 |
Jun 2012 |
Construction - Active |
UMCP | BIO-PSYCHOLOGY ROOM 2101 RENOVATIONS | $90,000 |
Oct 2011 |
Apr 2012 |
May 2012 |
Construction - Active |
UMCP | BIO-PSYCHOLOGY ROOM 4148 RENOVATIONS | $375,000 |
Mar 2011 |
Sep 2011 |
Apr 2012 |
Construction - Active |
UMCP | CAMPUS GENERAL PURPOSE CLASSROOM LIGHTING/OCCUPANCY SENSORS | $600,000 |
NA |
May 2011 |
Jan 2012 |
Construction - Active |
UMCP | CENTER FOR EDUCATIONAL PARTNERSHIP NORTH WING/VAR. RMS. RENV | $150,000 |
NA |
Jan 2012 |
May 2012 |
Construction - Active |
UMCP | CHESTERTOWN 3RD/4TH FL.HALL - CUMBERLAND 2ND FL.HALL ABATEMN | $6,600 |
NA |
Jun 2010 |
Jun 2010 |
Construction - Active |
UMCP | CHILLER REPLACEMENT FOR CEP | $264,867 |
Dec 2011 |
Apr 2012 |
Jun 2012 |
Construction - Active |
UMCP | COMCAST CENTER EDG RETROFIT | $150,000 |
NA |
NA |
NA |
Construction - Active |
UMCP | COMP & SPACE SCI - WING 2 -2ND FL. PHASE 3 OFC REN FOR JQI. | $466,000 |
Aug 2011 |
Apr 2012 |
Jul 2012 |
Construction - Active |
UMCP | COVERT LIBRARY STORAGE AREA | $243,000 |
Jul 2011 |
Apr 2012 |
Jul 2012 |
Construction - Active |
UMCP | ENERGY RESEARCH ROOM 0202A (0208) RENOVATIONS | $40,000 |
Aug 2011 |
May 2012 |
May 2012 |
Construction - Active |
UMCP | ESTIMATE REMOVE FIXED SEATING & MISC ITEMS | $32,751 |
NA |
May 2012 |
Jun 2012 |
Construction - Active |
UMCP | ESTIMATE FOR SCOPE OF WORK | $6,000 |
NA |
May 2012 |
May 2012 |
Construction - Active |
UMCP | ESTIMATE REMOVE RISER FRONT OF ROOM 1243 | $11,891 |
NA |
May 2012 |
Jun 2012 |
Construction - Active |
UMCP | LAB FOR PHYSICAL SCIENCES MISC. WORK | $66,000 |
NA |
Mar 2011 |
Jul 2011 |
Construction - Active |
UMCP | LEE #071 REPLACE 8 SETS OF RISER PIPES | $287,000 |
Feb 2012 |
Apr 2012 |
May 2012 |
Construction - Active |
UMCP | MCKELDIN LIBRARY 2ND FLOOR PORTICO DOOR RENOVATIONS | $55,000 |
NA |
Nov 2011 |
Feb 2012 |
Construction - Active |
UMCP | MITCHELL BUILDING SUITE 1130 RENOVATIONS ESTIMATE | $450,000 |
Jun 2011 |
Jan 2012 |
May 2012 |
Construction - Active |
UMCP | MORRILL HALL TESTING CTR 0105 FOR DR. GOUPELL | $168,300 |
Oct 2011 |
Jan 2012 |
May 2012 |
Construction - Active |
UMCP | OIT/NTS DATA & TELEPHONE NETWORK CLOSET REFRESH/REWIRE | $2,500,000 |
NA |
Apr 2009 |
Jun 2014 |
Construction - Active |
UMCP | ONE 60" MONITOR NEEDS TO BE MOUNTED RMS 3102 B & C | $1,825 |
NA |
May 2012 |
May 2012 |
Construction - Active |
UMCP | PROVIDE ESTIMATE FOR SCOPE OF WORK | $60,000 |
NA |
Apr 2012 |
Jun 2012 |
Construction - Active |
UMCP | RENOVATION TO WOMEN'S BASKETBALL LOCKER ROOM / LOUNGE | $67,000 |
NA |
Apr 2012 |
Jun 2012 |
Construction - Active |
UMCP | SKINNER - CONVERT LAB SPACE TO OFFICE AND RESEARCH SPACE | $100,000 |
NA |
Apr 2012 |
May 2012 |
Construction - Active |
UMCP | TALIAFERRO - MANAGE ROOM RENOVATIONS | $64,000 |
NA |
Nov 2011 |
May 2012 |
Construction - Active |
UMCP | VAN MUNCHING HALL MULTI-ROOM INTERIOR DESIGN ASSISTANCE | $250,000 |
Feb 2012 |
May 2012 |
Jul 2012 |
Construction - Active |
UMCP | VPR SURGING TO 4TH FLOOR OF SUSQUEHANNA | $6,137 |
NA |
May 2012 |
May 2012 |
Construction - Bidding |
UMCP | ART/SOC DEPT OF SOCIOLOGY SEEKING TO DEMOLISH INTERI WALLS | $125,000 |
Feb 2012 |
May 2012 |
Jul 2012 |
Construction - Bidding |
UMCP | AVW RM 1202 PLAN TO REROUTE RETURN WATER FRM CRAC UNIT | $37,956 |
Mar 2012 |
Jun 2012 |
Jul 2012 |
Construction - Bidding |
UMCP | CAMPUS FARM HEAVY USE AREA AND MANURE STORAGE AREA | $0 |
NA |
NA |
NA |
Construction - Bidding |
UMCP | HJP #073 CMNS TO DEVELOP ELECTRICAL & MECHANICAL PLANS | $155,000 |
Dec 2012 |
May 2012 |
Aug 2012 |
Construction - Bidding |
UMCP | MAIN ADMIN - GROUND FLOOR RENOVATION | $1,900,000 |
Sep 2011 |
May 2012 |
Nov 2012 |
Construction - Bidding |
UMCP | MAIN ADMIN - REN STE 1132 FOR VP OF ADMIN AFFAIRS | $303,000 |
Jan 2011 |
May 2012 |
Aug 2012 |
Construction - Bidding |
UMCP | PLANT SCIENCES - MSLA STUDIO PROJECT | $150,000 |
Feb 2012 |
Jun 2012 |
Aug 2012 |
Construction - Pending |
UMCP | CHEMISTRY EXPLOSION LAB 1308 | $0 |
NA |
NA |
NA |
Construction - Pending |
UMCP | COLE - DEMO EXISTING DOOR INTO OFFICE & FRAMED OPENING | $42,000 |
Dec 2011 |
Jul 2012 |
Aug 2012 |
Construction - Pending |
UMCP | CONVERT RECEPTABLE ROOM 1310B | $1,700 |
NA |
May 2012 |
May 2012 |
Construction - Pending |
UMCP | CSS WINGS 1 & 2 INSTAL NEW FCU TO REPLACE OLD UNTIS | $169,000 |
NA |
NA |
NA |
Construction - Pending |
UMCP | DEMO & RECONFIGURE MBB LOCKER ROOM | $35,000 |
NA |
NA |
NA |
Construction - Pending |
UMCP | ENGINEERING LAB 1144 & 1149 RENOVATIONS - LAB AREA ONLY | $430,000 |
Nov 2011 |
May 2012 |
Jul 2012 |
Construction - Pending |
UMCP | ESTIMATE - TO ADD A DUPLEX POWER RECEPTACLE | $1,700 |
NA |
NA |
NA |
Construction - Pending |
UMCP | ESTIMATE FOR FIXING 3 WALK-IN COOLER ROOMS | $65,000 |
NA |
May 2012 |
Jun 2012 |
Construction - Pending |
UMCP | ESTIMATE FOR SOUNDPROOFING 1117 THROUGH HVAC SYSTEM | $1,000 |
NA |
NA |
NA |
Construction - Pending |
UMCP | ESTIMATE INSERT VIEWING WINDOWS | $9,800 |
NA |
Jun 2012 |
Jun 2012 |
Construction - Pending |
UMCP | INSTALL 2 DOUBLE GANG OUTLETS | $2,200 |
NA |
NA |
NA |
Construction - Pending |
UMCP | INSTALL ACCESSIBLE RAMP/SIDEWALK | $25,000 |
NA |
Apr 2012 |
May 2012 |
Construction - Pending |
UMCP | INSTALL CHAIR RAIL IN ROOM 2126 | $1,040 |
NA |
Jul 2012 |
Jul 2012 |
Construction - Pending |
UMCP | INSTALL DEDICATED ELECTRICAL OUTLET - 3 POLE | $1,900 |
NA |
May 2012 |
NA |
Construction - Pending |
UMCP | INSTALL NEW CARPET AND PAINT | $5,500 |
NA |
Jun 2012 |
Jun 2012 |
Construction - Pending |
UMCP | INSTALLALLTION OF 4 OUTLETS IN ROOM 0135 | $1,100 |
NA |
May 2012 |
May 2012 |
Construction - Pending |
UMCP | JIMENEZ HALL RENOVATIONS MULTI ROOMS | $35,000 |
NA |
Jun 2012 |
Jun 2012 |
Construction - Pending |
UMCP | LEFRAK - CARPET & PAINT SUITE 1218 | $21,000 |
NA |
Jun 2012 |
Jul 2012 |
Construction - Pending |
UMCP | LEFRAK HALL MENS TOILET 0109 AND 1 WATER COOLER ADA MODS | $18,000 |
NA |
Jun 2012 |
Jul 2012 |
Construction - Pending |
UMCP | LEFRAK RM 0235 INSTALLATION OF FOUR CIRCUITS | $14,265 |
Feb 2012 |
NA |
NA |
Construction - Pending |
UMCP | LPS BUILDING A WOODEN PLATFORM | $3,000 |
NA |
NA |
NA |
Construction - Pending |
UMCP | MOUNT 47" LG MONITOR | $600 |
NA |
Apr 2012 |
Apr 2012 |
Construction - Pending |
UMCP | PERFORM SCOPE OF WORK IN ROOM 4201 | $1,360 |
NA |
May 2012 |
May 2012 |
Construction - Pending |
UMCP | PHYSICS BUILDING 0215 URINAL DEMOLISH, NEW URINAL INSTALL | $10,200 |
NA |
NA |
NA |
Construction - Pending |
UMCP | PROVIDE ESTIMATE FOR CONST. AND DESIGN IN MULTI ROOMS | $280,000 |
NA |
May 2012 |
Jul 2012 |
Construction - Pending |
UMCP | REPLACE EXISTING DIVIDER/PARTITION WALL RMS 3118 & 3120 | $17,500 |
NA |
May 2012 |
May 2012 |
Construction - Pending |
UMCP | REQUIRES TWO WALL OUTLETS RATED FOR 15AMPS ON WALL | $2,530 |
NA |
NA |
NA |
Construction - Pending |
UMCP | VMH FIRE IN LADIES RESTROOM 1503 | $25,000 |
NA |
Jun 2012 |
Jul 2012 |
Construction - Subst. Comp. |
UMCP | ART/SOC #146 FIRE/FLOOD IN STUDIO 3313 ON FEB 27, 2012 | $0 |
NA |
Mar 2012 |
Apr 2012 |
Construction - Subst. Comp. |
UMCP | BIO-PSYCH - GRND & 1ST FL REN FOR JCCSCMN - NSF GRANT | $1,733,714 |
Sep 2010 |
May 2011 |
Apr 2012 |
Construction - Subst. Comp. |
UMCP | CATHERINE GATELY TO WORK ON INTERIOR DESIGN ROOM 2203 | $60,000 |
Oct 2011 |
Nov 2011 |
Apr 2012 |
Construction - Subst. Comp. |
UMCP | COMPUTER SPACE SCIENCE JOINT QUANT INST PHASE 2 DESIGN/CONST | $1,898,515 |
Jun 2009 |
Jul 2010 |
Sep 2011 |
Construction - Subst. Comp. |
UMCP | ESTIMATE - TO SOUNDPROOF WALLS IN ROOM 4115E | $3,000 |
NA |
May 2012 |
May 2012 |
Construction - Subst. Comp. |
UMCP | ESTIMATE TO HAVE A HOT & COLD WATER SERVICE AND DRAIN | $5,000 |
NA |
Apr 2012 |
May 2012 |
Construction - Subst. Comp. |
UMCP | INSTALL ELECTRICAL LINE FOR TIME CLOCK | $1,600 |
NA |
May 2012 |
May 2012 |
Construction - Subst. Comp. |
UMCP | J. M. PATTERSON SUITE 2200 CLASSROOMS | $984,969 |
NA |
Nov 2011 |
Feb 2012 |
Construction - Subst. Comp. |
UMCP | LEFRAK HALL RM. 0208 RENOVATIONS | $169,030 |
Oct 2011 |
Jan 2012 |
Apr 2012 |
Construction - Subst. Comp. |
UMCP | MCK LIB ROOM 7111 MULTI PURPOSE INSTRUCTION LAB | $12,000 |
NA |
Apr 2012 |
May 2012 |
Construction - Subst. Comp. |
UMCP | MCK LIB UPGRADE FOR ROOMS 6101, 6103, 6107 TO INSTRUCT LABS | $16,000 |
NA |
Apr 2012 |
May 2012 |
Construction - Subst. Comp. |
UMCP | MCKELDIN LIBRARY - ORDER TEKNION COMPONENTS | $13,000 |
NA |
Jan 2012 |
Mar 2012 |
Construction - Subst. Comp. |
UMCP | MCKELDIN LIBRARY B0105 STAFF LOUNGE COUNTER TOPS RENV. ESTIM | $10,400 |
NA |
Mar 2012 |
Apr 2012 |
Construction - Subst. Comp. |
UMCP | MICROBIOLOGY BUILDING REPLACEMENT OF AIR HANDLERS | $2,255,652 |
NA |
Feb 2011 |
Jan 2012 |
Construction - Subst. Comp. |
UMCP | MINOR RENOVATIONS TO 2305 SUITE | $40,000 |
NA |
Apr 2012 |
May 2012 |
Construction - Subst. Comp. |
UMCP | MITCHELL BUILDING ROOM 3120 RENOVATIONS | $275,000 |
Jan 2011 |
Aug 2011 |
Jan 2012 |
Construction - Subst. Comp. |
UMCP | MMH PHASE THREE - OFFICE SUITES | $952,895 |
Jan 2011 |
May 2011 |
Oct 2011 |
Construction - Subst. Comp. |
UMCP | NYUMBURU - INSTALL VGA COMPUTER JACKS & REPAIR, PAINT WALL | $7,500 |
NA |
Jan 2012 |
Jan 2012 |
Construction - Subst. Comp. |
UMCP | PATAPSCO RMS. 2119, 2129, 2141, 2143 LAB SPACE RENOVATIONS | $1,200,000 |
Oct 2010 |
Feb 2011 |
Aug 2011 |
Construction - Subst. Comp. |
UMCP | REMOVAL OF HEATING UNIT | $350 |
NA |
Mar 2012 |
Mar 2012 |
Construction - Subst. Comp. |
UMCP | ROOM 4265 INSTALL WINCH AND MOUNTPLATE | $5,000 |
NA |
Feb 2012 |
Feb 2012 |
Construction - Subst. Comp. |
UMCP | TYDINGS - RENOVATE SUITE 3114 | $90,000 |
NA |
Feb 2012 |
May 2012 |
Design - Active |
UMCP | ARCHITECTURE STUDIO PHASE II DESIGN | $500,000 |
Feb 2012 |
May 2012 |
Aug 2012 |
Design - Active |
UMCP | AVRUM GUDELSKY - AHU 7 & 8 REPLACEMENT FOR VET. MED. | $2,000,000 |
Dec 2011 |
Oct 2012 |
Jan 2013 |
Design - Active |
UMCP | BENJAMIN BUILDING TOILET ROOMS RENOVATIONS ESTIMATE | $360,000 |
Mar 2012 |
Jul 2012 |
Oct 2012 |
Design - Active |
UMCP | CHESAPEAKE 3115G & 3115K DESIGN OFFICE FURNITURE | $17,000 |
Feb 2012 |
Aug 2012 |
Sep 2012 |
Design - Active |
UMCP | CSPA REQUEST EST TO REPLACE SEATING IN KAY THEATRE/600 SEATS | $0 |
May 2012 |
NA |
NA |
Design - Active |
UMCP | FRANCIS SCOTT KEY 0108,0112,1108,1114,3RD FLR FOUNT.ADA MODS | $72,000 |
Mar 2012 |
NA |
NA |
Design - Active |
UMCP | H. J. PATTERSON CLASSROOM 2242 COLLABORATIVE LEARNING RENOV. | $38,500 |
Feb 2012 |
Aug 2012 |
Nov 2012 |
Design - Active |
CARB | IBBR BUILDINGS 1A & 1B EMERGENCY POWER ASSESMENT/UPGRADE | $705,000 |
Mar 2011 |
Jun 2012 |
Jul 2012 |
Design - Active |
UMCP | JIMENEZ HALL LECTURE HALL 0220 RENOVATIONS | $75,000 |
Jan 2012 |
Jul 2012 |
Nov 2012 |
Design - Active |
UMCP | LEE BLDG REVIEW & ESTIMATE FOR RENOVATION OF ROOMS | $280,000 |
Jan 2012 |
Jun 2012 |
Aug 2012 |
Design - Active |
UMCP | LEFRAK - RENOVATIONS TO CRIM AND GEOG. DEPTS. | $737,000 |
Jan 2012 |
Aug 2012 |
Nov 2012 |
Design - Active |
UMCP | LEFRAK HALL 0231 AND 0233 SCHEMACTIC DESIGN | $25,000 |
Apr 2012 |
NA |
NA |
Design - Active |
UMCP | MARIE MOUNT HALL ROOMS 2100 / 2110 FURNITURE DESIGN SERVICES | $150,000 |
Dec 2011 |
Jun 2012 |
Jun 2012 |
Design - Active |
UMCP | MCKELDIN LIB EST OPTIONS TO REDESIGN LAYOUT RM 6131 | $0 |
Mar 2012 |
Sep 2012 |
Sep 2012 |
Design - Active |
UMCP | MISCELLANEOUS GENERAL INTERIOR DESIGN SERVICES FOR O & M | $0 |
NA |
NA |
NA |
Design - Active |
UMCP | SOUTH CAMPUS DINING HALL GREASE ABATEMENT SYSTEM RENOV. EST. | $12,000 |
Aug 2011 |
NA |
NA |
Design - Active |
UMCP | TALIAFERRO HALL 0104,0106,1129,1127, WATER COOLER ADA MODS | $36,000 |
Mar 2012 |
Jul 2012 |
Aug 2012 |
Design - Active |
UMCP | VAN MUNCHING RM 1517 RUDY'S CAF'E | $57,000 |
Mar 2012 |
Sep 2012 |
Jan 2013 |
Design - Active |
UMCP | WOODS HALL 0114, 0117, 1114, 1134, 1135 ADA MODS | $28,000 |
Mar 2012 |
Jul 2012 |
Aug 2012 |
Design - Pending |
UMCP | COLE FIELD HOUSE SUITE 0105,0117,0119,0119A RENOV. ESTIMATE | $360,000 |
May 2012 |
Sep 2012 |
Feb 2013 |
Design - Pending |
UMCP | MORRILL HALL MAIN ENTRANCE WOOD PORCH FLOOR/STAIR DESINGN | $300,000 |
Feb 2011 |
Jul 2011 |
Aug 2011 |
Design - Pending |
UMCP | VET SCI. PROVIDE EST TO UPGRADE HVAC SYSTEM IN RMS 1131&1129 | $100,000 |
NA |
NA |
NA |
Total: 110 |
Projects |
$26,429,848 |
||||
|---|---|---|---|---|---|---|